November 2019

ACMA

November 2019 Workers installing underground detention system at ACMA.

Work Completed

  • Delivery of trusses and steel
  • Underground detention system
  • Elevator pit

Work Underway

  • Preparation for concrete slab
  • Area A underground plumbing and electrical
  • Drain mat on stem walls

Substantial Completion: August 2021

General Contractor: Robinson Construction
Architect: DLR Group