October 2019

ACMA

Aerial of the New ACMA Site - Looking North with the Theater

Work Completed

  • Concrete footings formed
  • Abandoned oil tank emptied and removed

Work Underway

  • Footings being placed
  • Underground site utilities
  • Filling of old basement area
  • Delivery of trusses and steel

Substantial Completion: August 2021

General Contractor: Robinson Construction
Architect: DLR Group