Translate

Elementary School Projects

A-F

Aloha-Huber Park K-8

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Roof Repair

Application of spray-on membrane to entire roof.
Budget: $650,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 08/2019
Status: In Progress

Other 2014 Bond Projects

Building doors and hardware upgrades; replace the boiler; replace manual backboard hoists with electric hoists.

Barnes

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; replace exterior wood-framed windows with aluminum frames; replace manual backboard hoists with electric hoists.

Beaver Acres

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Seismic Upgrades

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; replace rooftop units.

Bethany

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Kindergarten Playground Repairs

Replace kindergarten playground.
Final Cost: $89,470.00
Funding: Construction Excise Tax 
Schedule: 12/2017 - 03/2018
Status: Complete

Repipe

Replace domestic water lines throughout the building; replace hot water heaters and structural infill under slab.
Final Cost: $1,079,000.00
Funding: 2014 Bond
Schedule: 06/2018 - 08/2018
Status: Complete

School Kitchen Improvements

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; parking lot slurry seal and repaving; covered play area re-paved; replace manual backboard hoists with electric hoists; replace carpet and rubber cove base in portable.

Bonny Slope

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades.

Cedar Mill

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Electrical Upgrades

Install new 3-phase electrical service, switchgear and electrical panels.
Budget: $489,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

HVAC System Upgrade

Install new HVAC systems throughout main building.
Budget: $2,500,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

New Playground Structures

Retrofit and replace playground components.
Final Cost: $31,600.00
Funding: 2014 Bond
Schedule: 04/2015 - 08/2015
Status: Complete

Roofing

Install new roofing on main building.
Budget: $953,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

Seismic Upgrades

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades.

Chehalem

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace playground structure, swings and refurbish surfacing.
Final Cost: $114,100.00
Funding: 2014 Bond
Schedule: 06/2018 - 08/2018
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace failing clock system; replace existing manual backboard hoists with electric hoists; renovate seclusion room.

Cooper Mountain

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Seismic Upgrades

Visit the project page for more information.

Other 2014 Bond Projects

Replace damaged doors and hardware.

Elmonica

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

2018 Portable Moves

Move to Elmonica ES from Five Oaks MS.
Final Cost: $260,680.00
Funding: Construction Excise Tax 
Schedule: 2018
Status: Complete

Rooftop Unit Replacement

Replace rooftop HVAC units on the A wing.
Final Cost: $187,300.00
Funding: 2014 Bond
Schedule: 06/2018 - 10/2018
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace boiler system; remove trees in bus lane obstructing field of view.

Errol Hassell

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; replace boiler system; replace failing clock system; repair damaged paving and re-stripe; replace damaged flooring in the portable restrooms.

Findley

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Playground Refurbishment

Replace specific components and replenish engineered wood fiber. 
Budget: $46,000.00
Funding: 2014 Bond
Schedule: Summer 2019
Status: In Progress

Other 2014 Bond Projects

Building doors and hardware upgrades; replace failing VCT gym floor with rubber Mondo floor; replace damaged restroom partitions with new partitions; various repairs to portables.

Fir Grove

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Drainage Repairs

Repair drainage around playground structures.
Final Cost: $148,500.00
Funding: Construction Excise Tax 
Schedule: 06/2016 - 09/2016
Status: Complete

Replace Playground Structures

Retrofit and/or replace damaged components to meet compliance.
Final Cost: $52,000.00
Funding: 2014 Bond
Schedule: 06/2016 - 09/2016
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace stage rigging; replace carpet in portables one and two; replace failing clock system; parking lot asphalt repairs.

G-O

Greenway

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Drainage Repairs

Repair drainage around playground structures.
Final Cost: $332,900.00
Funding: Construction Excise Tax 
Schedule: 06/2016 - 11/2016
Status: Complete

Replace Playground Structures

Retrofit and/or replace damaged components to meet compliance.
Final Cost: $74,700.00 
Funding: 2014 Bond
Schedule: 06/2016 - 11/2016
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace stage curtains; replace boiler system; replace failing clock system; renovate seclusion room.

Hazeldale

Building Replacement

Visit the project page for more information.

2016 Portable Moves

Move to Hazeldale ES from Vose ES.
Final Cost: $90,120.00
Funding: Construction Excise Tax
Schedule: 2016
Status: Complete

Other 2014 Bond Projects

Replace failing clock system.

Hiteon

Chiller Replacement

Replace chiller and associated systems.
Final Cost: $186,400.00
Funding: 2014 Bond
Schedule: 06/2018 - 03/2019
Status: Complete

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Refurbish playground.
Final Cost: $359,500.00
Funding: 2014 Bond
Schedule: 06/2017 - 10/2017
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace manual backboard hoists with electric hoists.

Jacob Wismer

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Fire Alarm System Upgrades

Remove and replace all devices, fire alarm panel and power supplies.
Final Cost: $196,000.00
Funding: 2014 Bond
Schedule: 06/2015 - 08/2015
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; gym roof truss repair.

Kinnaman

Chiller Replacement

Replace chiller and associated systems.
Final Cost: $186,400.00
Funding: 2014 Bond
Schedule: 06/2018 - 03/2019
Status: Complete

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Rooftop Heat Pump Replacement

Replace HVAC units on the B wing.
Final Cost: 68,600.00
Funding: 2014 Bond
Schedule: 09/2017 - 11/2017
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; renovate seclusion room; replace portable wood decking with aluminum decking.

McKay

ADA Upgrades

Visit the project page for more information.

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; renovate staff restrooms and repair plumbing issues.

McKinley

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace playground structure and refurbish surfacing.
Final Cost: $94,000.00
Funding: 2014 Bond
Schedule: 07/2017 - 09/2017
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; repair/replace student restroom partitions; replace damaged flooring in portable restrooms; replace damaged asphalt pathway.

Montclair

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace playground structures and refurbish surfacing.
Final Cost: $52,500.00
Funding: 2014 Bond
Schedule: 07/2018 - 10/2018
Status: Complete

2014 Portable Moves

Move to Montclair ES from Sunset HS.
Final Cost: $145,000.00
Funding: 2014 Bond
Schedule: 2014
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace carpet and rubber cove base in ten classrooms; replace failing clock system; replace existing manual backboard hoists with electric hoists.

Nancy Ryles

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades.

Oak Hills

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace playground structure and add drainage in playground area.
Final Cost: $148,900.00
Funding: 2014 Bond
Schedule: 07/2017 - 09/2017
Status: Complete

New Kitchen Freezer

Replace kitchen freezer and update components.
Final Cost: $148,300.00
Funding: 2014 Bond
Schedule: 07/2017 - 09/2018
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades.

P-Z

Raleigh Hills K-8

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Raleigh Hills K-8 Improvements

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; install acoustic panels in gym; sewer repair; siding replacement.

 

Raleigh Park

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace and refurbish play structures.
Final Cost: $140,700.00
Funding: 2014 Bond
Schedule: 07/2018 - 09/2018
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace stage curtains; replace areas of hallways and failing gym floor with new flooring.

Ridgewood

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Electrical Upgrades

Install new 3-phase electrical service, switchgear and electrical panels.
Budget: $1,195,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

HVAC System Upgrade

Install new HVAC systems throughout main building.
Budget: $3,365,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

New Playground Structures

Retrofit, replace structures, refurbish surfacing and add drainage.
Final Cost: $59,100.00
Funding: 2014 Bond
Schedule: 07/2016 - 09/2017
Status: Complete

Parking Lot Repair & Slurry Seal, Resurface Track

Repave rear bus loop and resurface track.
Final Cost: $136,700.00
Funding: 2014 Bond
Schedule: 08/2016 - 10/2017
Status: Complete

Freezer Replacement

Visit the School Kitchen Improvements project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; boiler replacement.

Rock Creek

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Drainage Repairs

Repair drainage around playground structures.
Final Cost: $174,700.00
Funding: Construction Excise Tax 
Schedule: 06/2016 - 08/2016
Status: Complete

Playground Replacement

Remove and replace all playground equipment.
Final Cost: $205,400.00
Funding: 2014 Bond
Schedule: 06/2016 - 08/2016
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; portable carpet replacement; remodel restrooms in main building for ADA compliance and new fixtures.

Sato

New Building

Visit the project page for more information.

Scholls Heights

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Playground Refurbishment

Replace specific components and replenish engineered wood fiber. 
Budget: $20,000.00
Funding: 2014 Bond
Schedule: Summer 2019
Status: In Progress

Other 2014 Bond Projects

Building doors and hardware upgrades; renovate seclusion room.

Sexton Mountain

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Fire Alarm Detectors

Remove and replace all devices, fire alarm panel and power supplies to bring system up to code requirements.
Final Cost: $286,000.00
Funding: 2014 Bond
Schedule: 06/2015 - 08/2015
Status: Complete

Roof Replacement

Replace standing seam metal roofing over the library, gym and cafeteria.
Final Cost: $935,700.00
Funding: 2014 Bond
Schedule: 06/2018 - 09/2018
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades.

Springville K-8

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Springville K-8 Improvements

Visit the project page for more information.

2014 Portable Moves

Move to Springville ES from Sunset HS.
Final Cost: $134,100.00
Funding: 2014 Bond
Schedule: 2014
Status: Complete

2015 Portable Moves

Move to Springville ES from Hazeldale ES.
Final Cost: $152,600.00
Funding: 2014 Bond
Schedule: 2015
Status: Complete

Other 2014 Bond Projects

Building doors and hardware upgrades; replace boiler.

Terra Linda

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

Other 2014 Bond Projects

Building doors and hardware upgrades; replace damaged asphalt sidewalk; replace existing manual backboard hoists with electric hoists.

Vose

Building Replacement

Visit the project page for more information.

West Tualatin View

District-Wide Interior Classroom Locks

Visit the project page for more information.

District-Wide Security Upgrades

Visit the project page for more information.

District-Wide Unified Communication System

Visit the project page for more information.

New Playground Structures

Replace worn structure and construct ADA access.
Final Cost: $150,400.00
Funding: 2014 Bond
Schedule: 07/2016 - 09/2016
Status: Complete

Roof Replacement

Re-roof school, full tear-off.
Budget: $1,400,000.00
Funding: 2014 Bond
Schedule: 06/2019 - 09/2019
Status: In Progress

Other 2014 Bond Projects

Building doors and hardware upgrades; reconstruct damaged wood flooring and walls in portable.

William Walker

Building Replacement

Visit the project page for more information.