Five Oaks Middle School

North Student Restroom Interior

Work Completed

  • Main office vestibule
  • North student restrooms
  • Salvaged bleacher wood wall graphic
  • Phase 5 (west classroom wing) classroom lighting, markerboards, A/V technology and carpet
  • Phase 5 staff and unisex restrooms tiling
  • Exterior building soffit LED lights

Work Underway

  • Phase 5 casework and wood paneling
  • Phase 6 (special education wing) demolition
  • Main corridor ceiling and lighting
  • Commons concrete polishing
  • Salvaged maple wood wall graphic
  • Painted and digital wall covering graphics
  • North garden fencing

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout