January 2019

Five Oaks Middle School

Workers install window joint sealant at Five Oaks Middle School

Work Completed

  • Electrical, HVAC and plumbing rough-in for administration office and Northeast addition
  • Exterior wall framing in Northeast addition
  • Exterior stud and interior framing for administration office
  • Structural steel and roof decking for Northwest addition
  • Exterior weather barrier and flashing
  • Painting for Northeast remodel

Work Underway

  • Doors and frames for administration office
  • Restroom tile and grout for Northeast remodel
  • Ceiling grid install for Northeast remodel
  • Window install for Northeast addition
  • Exterior masonry work for Northeast addition
  • Audio/visual rough-in for Northeast addition

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects