July 2020

Five Oaks Middle School

Stair Railing at Five Oaks Middle School.

Work Completed

  • Phase 6 (southeast wing) classroom carpet and rubber base
  • Phase 6 ceilings and wood paneling
  • Front entrance sidewalks and grass seeding
  • Phase 7 (science wing) classroom paint
  • D Wing student restroom

Work Underway

  • Phase 7 wall framing
  • Phase 7 window framing and waterproofing
  • Commons student restroom
  • Staff courtyard fence panels
  • Commons stair railing panels

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects