June 2019

Five Oaks Middle School

Work Completed

  • Demo in Phases 3 and 4
  • Phase 3 plumbing slab saw cutting
  • Phase 3 wall framing and door frames
  • Phase 4 library skylight opening
  • Filled the library pit in Phase 4 with concrete
  • Masonry pillars down administration corridor

Work Underway

  • Vestibule concrete footings
  • Above ceiling rough-in for Phase 4
  • Phase 4 plumbing saw cutting
  • Phase 3 electrical wall rough-in
  • Blocking in walls for Phase 3
  • Installing drywall in Phase 3
  • Cutting open Phase 3 HVAC penetrations

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects