June 2020

Five Oaks Middle School

New garden courtyard fencing at Five Oaks Middle School.

Work Completed

  • Phase 6 (southeast wing) classroom TV mounts and speakers
  • Phase 7 (science wing) concrete polishing
  • Garden courtyard fencing
  • Student restroom tile
  • Front entrance ADA sidewalk access

Work Underway

  • Phase 6 ceiling grid and wood paneling 
  • Phase 7 classroom paint
  • Phase 7 sanitary branch line scoping
  • Phase 7 corridor ceiling tile
  • Staff courtyard fence panels
  • Commons stair railing panels

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects