March/April 2020

Five Oaks Middle School

March/April 2020 - Construction crew working on replacing the main sanitary line in the science wing at Five Oaks Middle Scho

Work Completed

  • Commons concrete polishing
  • Science wing main sanitary line replacement
  • Phase 6 (southeast wing) wall framing and equipment blocking
  • Phase 7 (science wing) moved out staff in preparation for early work
  • Life skills plumbing sawcutting
  • Student restrooms demolition
  • Courtyard garden landscaping

Work Underway

  • Commons stair railing
  • Phase 6 wall insulation, door frames, HVAC, electrical, plumbing rough-ins
  • Phase 7 demolition
  • Corridor ceiling replacement throughout school
  • Leveling concrete floor in student restrooms
  • Painted and digital wall covering graphics

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects