Construction Updates header
May 2020

Five Oaks Middle School

Upgrading ADA accessibility on the front sidewalk at Five Oaks Middle School.

Work Completed

  • Student restroom demolition
  • Student restroom wall framing
  • Administration corridor ceiling
  • Phase 7 (science wing) teaching wall blocking
  • Courtyard fence posts

Work Underway

  • Front sidewalk 
  • Stormwater line
  • Phase 6 (southeast wing) painting
  • Phase 7 AV speakers
  • Phase 7 concrete polishing
  • Front office storefront windows
  • East main corridor ceiling

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects