October 2019

Five Oaks Middle School

October 2019 – Garden and stormwater facility work progressing on the east side at Five Oaks Middle School.

Work Completed

  • Phase 5 demolition
  • Vestibule storefront roofing
  • Vestibule framing
  • Site light poles
  • West garden paving and benches

Work Underway

  • Phase 5 slab sawcutting
  • Phase 5 HVAC, electrical, plumbing rough-ins
  • Vestibule glazing
  • East garden paving
  • East garden stormwater runnel

Substantial Completion: December 2020

General Contractor: Kirby Nagelhout
Architect: Bassetti Architects