January 2019

William Walker Elementary School

William Walker Elementary School 

Aerial of construction of William Walker Elementary School
Work Completed: 
  • Underground plumbing and electrical
  • Slab for gym, library and kindergarten area
  • Precast wall installation
  • Framing in kitchen
  • Second floor slab for South classrooms
  • Roof decking in gym
  • New intersection signal activation
Work Underway:
  • Steel installation
  • HVAC, plumbing and electrical in Administration Office and Special Education classrooms
  • Metal studs for framing in Administration Office and Special Education classrooms
  • Grading for covered play area
  • Improvements on Lynnfield Lane
 

Substantial Completion: August 2019

General Contractor: Kirby Nagelhout
Architect: DLR Group