March 2019

William Walker Elementary School

Aerial of william walker ES

Work Completed: 

  • Roofing above South classroom wing
  • Concrete placement in stage area
  • Decking in North classrooms
  • Sheetrock in administrative office and Special Education areas

Work Underway:

  • Roofing above gym and cafeteria
  • Preparation for concrete slab in gym and cafeteria
  • Interior framing in 2nd floor North and South classrooms
  • HVAC, fire sprinkler, electrical and plumbing rough-in in various areas
  • Siding installation
 

Substantial Completion: August 2019

General Contractor: Kirby Nagelhout
Architect: DLR Group