June 2019

William Walker Elementary School

Front exterior of William Walker Elementary School.

Work Completed: 

  • HVAC rooftop units
  • Siding and exterior window installation
  • Covered play roof

Work Underway:

  • Ceiling grid, lighting fixtures and sprinklers
  • Generator installation and power distribution
  • Tiling and flooring
  • Toilet accessories
  • Doors and blinds
  • Concrete polishing
  • Wainscot and casework
  • Grading, curbs and sidewalks in west parking lots
  • Sidewalk and landscaping on Lynnfield Ln.
 

Substantial Completion: August 2019

General Contractor: Kirby Nagelhout
Architect: DLR Group