The William Walker Elementary School replacement project is progressing well. All concrete slabs are in place. Roofing, exterior siding and windows are about 60-75% complete. Dry wall in the office and Special Education wing is complete and in progress in 2nd floor south classrooms sector.

Interior framing, HVAC, plumbing and electrical rough-in is in progress in the north classrooms sector. Work continues in the covered play area and Lynnfield Lane. The access road through Cedar Hills Park is constructed and the signal at Cedar Hill Blvd & Huntington Ave is activated.